Statement of work template: what a good SOW includes

A free statement of work template in Word for consultancy, software and systems integration work, with the sections that prevent the usual arguments.

By Christopher Fagan, Managing Partner, PEF Consulting Partners

A note before you start

A statement of work is where most supplier disputes start, usually because a deliverable was described as an activity, acceptance was never defined or the assumptions were buried. Describe outputs rather than effort, say how each one will be accepted, and make the assumptions and client responsibilities as visible as the price. If both sides cannot read it the same way, it is not finished.

Christopher Fagan, Managing Partner, PEF Consulting Partners

How to use this template

Write deliverables as things you can inspect, each with acceptance criteria and a named person who signs it off. List assumptions and client responsibilities explicitly, because they drive most change requests. Tie payments to accepted deliverables or milestones rather than time where you can. Agree change control before work starts. The SOW normally sits under a master services agreement that carries the legal terms, so check both with your legal adviser.

PEF Consulting Partners

Statement of Work

[Organisation name] | Version 0.1 | [Date] | Owner: [Name, role]

1. Parties and background

Item Detail
Client  
Supplier  
Master agreement reference  
Background  

2. Objectives and scope

In scope Out of scope
   
   
   
   
   

3. Deliverables and acceptance

Deliverable Description Acceptance criteria Accepted by Due date
         
         
         
         
         

4. Milestones and timeline

Milestone Date Dependency
     
     
     
     
     

5. Roles and client responsibilities

Responsibility Owner (client or supplier) Notes
     
     
     
     
     

6. Assumptions

Assumption Impact if untrue
   
   
   
   
   

7. Fees and payment

Milestone or period Amount (excluding VAT) Invoice trigger
     
     
     
     

8. Change control

[Either party may request a change in writing. The supplier will assess the impact on scope, time and cost within five working days. No change takes effect until both parties sign a change note.]

9. Governance and reporting

Forum Frequency Attendees
     
     
     

10. Signatures

Name Role Organisation Signature Date
         
         

Template by PEF Consulting Partners, pefconsultingpartners.co.uk. Free to use and adapt.

Related reading: the decision log and change request template, the RFP template for software selection, software procurement and selection, how PEF prices its own work.

Common questions

What is a statement of work?

A document that defines a specific piece of work between a client and a supplier: the scope, deliverables, acceptance, timeline, responsibilities, assumptions and fees. It usually sits under a master services agreement that holds the legal terms.

What is the difference between a statement of work and a scope of work?

A scope of work describes the work itself. A statement of work wraps the scope with everything needed to contract for it, including acceptance, timeline, fees, assumptions and change control.

What is the difference between an SOW and a contract?

The contract, often a master services agreement, sets the legal relationship: liability, intellectual property, termination and payment terms. Each SOW defines one piece of work under it.

Who writes the statement of work?

Usually the supplier drafts it and the client edits it. The client should always write or rewrite the acceptance criteria and the client responsibilities, because that is where risk quietly moves.

If you are about to sign a large systems integration SOW, an independent read of the deliverables, assumptions and acceptance criteria costs very little compared with the change requests it prevents.

Book a confidential conversation

PEF TRACK RECORD£13bnLargestprogramme led5Continentsdelivered across19 yrsSystems delivery£25mLargestsingle saving