Peter Kraljic’s portfolio model is still one of the quickest ways to decide where procurement effort should go. This guide shows how to score your spend, what each quadrant needs and how it plays out on a hypothetical technology and services portfolio.
By Christopher Fagan, Managing Partner, PEF Consulting Partners
Delivered for and alongside
















The Kraljic matrix is a two by two tool that sorts everything an organisation buys by two measures: profit impact, meaning how much an item affects cost, quality or revenue, and supply risk, meaning how hard it is to secure. Each of the four resulting quadrants calls for a different purchasing strategy and a different kind of supplier relationship.
Its value is focus. No procurement team can give every contract the same attention, and the matrix gives a defensible reason to concentrate on a handful of critical categories while running the rest efficiently. It also gives finance, operations and procurement a shared language for why one supplier gets a partnership and another gets a reverse auction.
In this article
Peter Kraljic set out the model in a 1983 Harvard Business Review article, Purchasing Must Become Supply Management. He was writing for companies facing raw material shortages, political turbulence in supply markets and fast technological change, and his argument was that buying could no longer be treated as an administrative task. Supply had become a strategic risk and needed to be managed as one.
The approach is often called the Kraljic portfolio purchasing model, because it treats purchases the way an investor treats a portfolio: different holdings need different handling. Kraljic described four stages.
In practice many teams stop after the first stage and use only the grid. The later stages are where much of the value sits, and they are built into the step by step method below.
The grid puts profit impact on one axis and supply risk on the other. That produces four groups, each with its own logic.
The quadrants describe categories of spend, not the worth of a supplier as a business. The same supplier can be non critical for one organisation and strategic for another.
The matrix is only as good as the scoring behind it. Agree the criteria with finance, operations and budget holders before anyone plots a point, and score each category on a simple scale such as 1 to 5.
Profit impact asks how much the category affects the results of the business. Useful criteria include:
Supply risk asks how hard the category is to secure on acceptable terms. Useful criteria include:
Weight the criteria if some matter more to you, and write down the reason behind each score. The written reasoning is what lets you defend the result and revisit it a year later.
Copy this table into a spreadsheet or category plan and adapt the wording to your organisation.
| Quadrant | Profit impact | Supply risk | Purchasing strategy | Supplier relationship | Main actions | Watch for |
|---|---|---|---|---|---|---|
| Strategic items | High | High | Secure long term value and supply | Partnership with senior sponsors on both sides | Joint plans, close performance management, contingency and exit planning, periodic market testing | Dependence that weakens your negotiating position over time |
| Leverage items | High | Low | Use buying power to reduce cost | Competitive and commercial | Aggregate demand, tender regularly, negotiate price structures, consider reverse auctions | Squeezing so hard that service or quality suffers |
| Bottleneck items | Low | High | Secure supply at acceptable cost | Stable, often longer term | Backup suppliers, buffer stock where relevant, longer contracts, specification changes that widen the market | Bottlenecks created by your own specifications |
| Non critical items | Low | Low | Reduce the cost of buying | Light touch and transactional | Standardise, consolidate suppliers, purchasing cards and simple ordering channels, automated approvals | Spending more on process than the items are worth |
For strategic items, add the second test of relative power. Where you hold the stronger position, press for better terms. Where power is balanced, invest in the relationship. Where the supplier dominates, look for ways to diversify, even if that takes years.
Take a hypothetical organisation reviewing its technology and services spend. The procurement lead and the finance director score eight categories from 1 to 5 on each axis, treating anything above 3 as high. The results are illustrative and not drawn from any real client.
| Category | Profit impact | Supply risk | Quadrant | Chosen strategy |
|---|---|---|---|---|
| Core ERP platform and support | 5 | 5 | Strategic | Executive sponsored partnership, roadmap reviews, renewal planning started two years ahead |
| Systems integrator for the transformation programme | 5 | 4 | Strategic | Outcome based milestones, named key people, independent assurance of progress |
| Cloud infrastructure | 4 | 2 | Leverage, drifting towards strategic | Committed spend negotiated against usage forecasts, portability designed into the architecture |
| Laptops and end user devices | 4 | 1 | Leverage | One standard specification, competitive tender every two to three years |
| Contract developers and testers | 4 | 2 | Leverage | Consolidated onto a small panel with agreed rate cards |
| Support for a legacy billing system | 2 | 5 | Bottleneck | Multi year support agreement, documentation and knowledge transfer, replacement on the roadmap |
| Specialist industry data feed | 2 | 4 | Bottleneck | Longer contract with price caps, alternative source identified and tested |
| Minor software subscriptions | 1 | 1 | Non critical | Single request route, duplicate tools removed, renewals aligned and automated |
Two findings stand out. Cloud infrastructure scores as leverage on paper, but every year spent building on one provider’s own services raises the cost of leaving, so the strategy deliberately keeps the exit open.
The legacy billing support is a bottleneck the organisation created itself by customising the system heavily years ago. No buying tactic fixes that. The answer is replacing the system, which turns a procurement problem into a programme decision best supported by independent software selection.
The matrix earns its place in annual category planning, before a major sourcing exercise, when deciding which suppliers need formal relationship management and when a new procurement leader needs a quick view of where the risk sits. It is also a clear way to explain priorities to a board on a single page.
It is less useful in four situations.
The grid is the segmentation step inside category management, where each position becomes a category plan with targets and owners. It also shows where to invest in supplier relationship management, since strategic and bottleneck suppliers usually need structured governance while routine suppliers do not.
The supply risk scores feed straight into third party risk management and into the risk register for critical services. For non critical items, the gains come from a clean procure to pay process rather than from negotiation, and when a strategic category comes up for renewal, a structured request for proposal keeps the comparison fair.
Our procurement consultancy uses this segmentation to decide where effort should go. We hold no reseller agreements and take no commissions from software vendors, so the strategy for each quadrant is set by your interests alone.
A Kraljic matrix is a procurement tool that sorts purchases into four groups by profit impact and supply risk: strategic, leverage, bottleneck and non critical items. Each group needs a different strategy, from close partnership for strategic items to simple, low cost buying for routine ones. Peter Kraljic introduced it in the Harvard Business Review in 1983.
Strategic items have high profit impact and high supply risk, so they need partnership and contingency planning. Leverage items have high impact but low risk, so you use buying power and competition. Bottleneck items have low impact but high risk, so the focus is security of supply. Non critical items are low on both, so the aim is efficient, low effort buying.
Both have high profit impact, but they differ on supply risk. Leverage items come from competitive markets with plenty of capable suppliers, so you can tender, aggregate volume and switch. Strategic items come from a few suppliers you cannot easily replace, so pressing too hard on price can damage a relationship you depend on. They need partnership, governance and contingency instead.
Focus on security of supply rather than price. Typical actions include qualifying a backup supplier, holding buffer stock where it applies, agreeing longer contracts with price protection, and changing the specification so more suppliers can meet it. Many bottlenecks are self inflicted, created by bespoke specifications or heavy customisation, so look inside the organisation as well as at the market.
Yes, as a way to segment spend and decide where procurement effort should go. Its limits are that the scoring relies on judgement, it shows only the buyer’s view of the relationship and it needs regular review as markets change. Used with good spend data, agreed criteria and a test of supplier power for strategic items, it remains one of the most practical tools available.
Related reading: Category management in procurement, Supplier relationship management, Third party risk management and Independent procurement consultancy.
We can score your categories with your team, test the strategic ones against the market and turn the result into plans with owners and dates.
Book a confidential conversation
Sources: Kraljic, P. (1983) Purchasing Must Become Supply Management. Harvard Business Review.
Written by Christopher Fagan