How to work out who can make or break a change, where each person stands and what you need from them, with a copyable template and a hypothetical worked example.
By Christopher Fagan, Managing Partner, PEF Consulting Partners
Delivered for and alongside
















Stakeholder analysis is the process of identifying everyone who can affect or will be affected by a change, assessing their interest, influence and current stance, and deciding how to engage each of them. Done properly, it tells a programme whose support it needs, where resistance will come from and who on the team owns each relationship.
Programmes rarely fail because nobody drew a plan. They stall because a decision maker was never really on board, a group that had to change its way of working was told too late, or someone with a quiet veto was missed entirely. Stakeholder work is how you find those people early, while there is still time to bring them with you.
In this article
A stakeholder is any person, group or organisation with an interest in the outcome or the power to shape it. That includes the obvious ones, such as the sponsor, the board and the teams whose work will change. It also includes the less obvious ones: regulators, unions, key suppliers, customers, auditors and the people who run the systems you plan to switch off.
The analysis has three jobs. It identifies who matters, it assesses each stakeholder on a few consistent dimensions, usually interest, influence and stance, and it turns that assessment into a decision about how, how often and by whom each one is engaged. The third job is the one most often skipped, and the one that makes the difference.
The stakeholder idea entered mainstream management through R. Edward Freeman’s 1984 book Strategic Management: A Stakeholder Approach. Freeman argued that organisations should be managed with regard to everyone who affects or is affected by them, not only their shareholders.
The power interest grid is usually credited to Mendelow, whose 1981 conference paper on environmental scanning applied the stakeholder concept to how organisations watch the world around them. Strategy textbooks later turned it into the grid most people use today. A useful alternative is the salience model of Mitchell, Agle and Wood, published in 1997, which ranks stakeholders by power, legitimacy and urgency.
Stakeholder mapping places each stakeholder on a simple chart so the team can see the whole picture at once. The most common version is the power interest grid, with power or influence on one axis and interest on the other. Each quarter suggests a default approach:
Two cautions apply. Power is not the same as seniority: the payroll manager who has to sign off parallel running, or the union representative whose members run the depots, can hold more practical influence than a director. Positions on the grid also move, so a map drawn at initiation and never revisited will mislead you by go live. Our stakeholder map template gives you a ready made grid to plot against.
The template below is a stakeholder analysis matrix: one row per stakeholder, with the same columns for everyone so they can be compared. The first row explains what goes in each column. Copy it into a spreadsheet, and treat the finished version as confidential, because candid notes on people’s positions are not for general circulation.
| Stakeholder | Role | Interest | Influence | Current stance | Desired stance | Engagement approach | Owner |
|---|---|---|---|---|---|---|---|
| Name or group | Their role in the organisation and in the change | What they care about and stand to gain or lose; high, medium or low | How far they can shape the outcome, and through what; high, medium or low | Opposed, sceptical, neutral, supportive or champion, with the evidence | Where you need them to be, and by when | How, how often and through which channel they will be engaged | The team member who owns the relationship |
This example is hypothetical. A regional utility is replacing the system that schedules its field engineers, and the operations director sponsoring the change plans to brief the workforce once the contract is signed. A short analysis changes that plan.
| Stakeholder | Role | Interest | Influence | Current stance | Desired stance | Engagement approach | Owner |
|---|---|---|---|---|---|---|---|
| Operations director | Sponsor | High: owns the productivity target | High | Champion | Champion | Fortnightly one to one; chairs the steering group | Programme director |
| Field engineers | Daily users of the new app | High: changes how their day is planned | Medium as a group | Sceptical | Supportive by the end of the pilot | Pilot depot, user group, early demonstrations | Change lead |
| Union representatives | Represent field staff | High: working patterns and use of location data | High | Neutral | Supportive | Early consultation on working practices and data use | HR director |
| Scheduling team lead | Runs the current scheduling desk | High: own role will change | High informally: trusted by engineers | Opposed | Supportive | Join the design team and shape the new desk role | Operations director |
| Finance director | Controls the budget | Medium: cost and benefits | High | Neutral | Supportive | Monthly benefits tracking; sign off at each gate | Programme director |
| Incumbent supplier | Runs the old system until exit | High: losing the contract | Medium: holds the data and exit support | Neutral | Cooperative through exit | Formal exit plan and regular service meetings | Commercial manager |
The matrix shows two things the sponsor had not planned for. The union representatives need consulting before the design is fixed, not after the contract is signed, because the new app changes how engineers’ time and location are recorded. And the scheduling team lead, whose own role is changing, has more influence with the engineers than anyone in management.
Bringing the team lead into the design turns the most likely source of resistance into the most credible voice for the change. Neither point would have surfaced from an organisation chart.
The matrix tells you what needs to happen; the stakeholder engagement plan says how. For each priority stakeholder it sets out the objective, the key messages, the channel, the frequency, the owner and how you will know it is working, such as attendance, the questions being raised or sentiment in the pilot. Our communication plan template gives you the structure.
Two other tools help. A RACI matrix settles who decides, who is consulted and who is informed, which removes a surprising amount of friction with senior stakeholders. For the people whose daily work is changing, the ADKAR model helps you plan what each group needs to move from awareness to lasting change, and the change curve is a reminder that dips in support are a normal part of change rather than a sign of failure.
Use it at the start of any change that affects how people work, before a business case goes to the board, before a major procurement and at mobilisation. Repeat it at each phase gate and whenever a programme stalls, because a stalled programme is very often a stakeholder problem dressed up as a technical one.
Keep it proportionate. A small team change needs a short conversation and a list, not a formal matrix. And do not treat it as a document to be produced: if the analysis is written once, filed and never used to decide who talks to whom, it has cost time and changed nothing.
Stakeholder work sits at the centre of change management. It shapes the sponsor’s role, and our guide to what a good programme sponsor does covers that relationship in detail. A change readiness assessment then tells you whether the people affected are ready, and our change management and adoption service puts the engagement plan into practice alongside your team rather than leaving it on paper.
It matters most where stakeholders are many and their interests pull in different directions. Few programmes test this harder than a national support scheme. Our Managing Partner, Christopher Fagan, was Project Director for the £9bn Energy Bills Support Scheme, delivered for Ofgem, BEIS and HMRC, carrying responsibility for the whole implementation and for protecting taxpayers’ money on its way to households, a programme with more stakeholders than most. In our experience, plans survive when the people who could stop them have helped to shape them.
Stakeholder analysis is the process of identifying the people and groups who can affect or are affected by a change, assessing each one’s interest, influence and current stance, and deciding how to engage them. Its output is usually a matrix of stakeholders and an engagement plan, with a named owner for each relationship, reviewed regularly as the change progresses.
A power interest grid is a two by two chart that plots stakeholders by how much power they have over a change and how interested they are in it. High power, high interest stakeholders are managed closely; high power, low interest are kept satisfied; low power, high interest are kept informed; low power, low interest are monitored. Positions move, so review the grid regularly.
Start by defining the change and what you need from people. List stakeholders widely, splitting broad groups into the parts that will react differently. Assess each on interest, influence and current stance, then decide the stance you need. Plot them on a grid, choose an engagement approach and an owner for each priority stakeholder, and review the analysis at every phase gate.
A useful template records, for each stakeholder, who they are, their role, their interest in the change, their influence over it, their current stance, the stance you need, the engagement approach and the team member who owns the relationship. Keeping the same columns for everyone makes stakeholders comparable, and the finished document should be treated as confidential.
Stakeholder analysis works out who matters, what they care about, how much influence they hold and where they stand. A stakeholder engagement plan turns that into action: objectives, messages, channels, frequency and owners for each priority stakeholder, plus how you will know the engagement is working. The analysis comes first and should be refreshed as the plan runs.
Related reading: Stakeholder map template, The ADKAR model explained, The change curve explained, Communication plan template and What a good programme sponsor does.
We help sponsors and programme teams work out who matters, plan the engagement and carry it through alongside your people. Talk to us about your programme.
Book a confidential conversation
Sources: R. Edward Freeman, Strategic Management: A Stakeholder Approach, 1984; A. L. Mendelow, Environmental Scanning: The Impact of the Stakeholder Concept, ICIS Proceedings, 1981; Ronald K. Mitchell, Bradley R. Agle and Donna J. Wood, Toward a Theory of Stakeholder Identification and Salience, Academy of Management Review, 1997
Written by Christopher Fagan
Managing Partner, PEF Consulting Partners
Christopher has led systems and transformation delivery for 19 years, including the National Grid separation, the £9bn Energy Bills Support Scheme and the BP Pulse EV charging rollout.