Hoshin kanri explained: policy deployment, catchball and the X matrix

A plain English guide to hoshin kanri: what it is, how catchball and the X matrix work, and a simplified template and planning cycle you can copy.

By Christopher Fagan, Managing Partner, PEF Consulting Partners

£13bnlargest programme delivered
19 yrssenior systems delivery
5 continentsdelivered across
£25msaving on a single programme

Delivered for and alongside

ShellBPCapitaBaringaOfgemSmart DCCInsightsFlui TechnologiesExxonMobilVodafoneConstellation SoftwareDeloittePwCEYNational GridElexon

Hoshin kanri is a strategy deployment method, developed in Japan, that turns a few long term breakthrough objectives into annual goals, projects and measures at every level of an organisation, and reviews them on a regular cycle. In English it is usually called policy deployment or hoshin planning.

The idea is simple: agree the few things that matter most, make sure everyone can see how their work contributes, and check progress often enough to correct course. Doing it well is harder. This guide explains how the method works, how to read an X matrix and the mistakes that make it fail, with a simplified template and planning cycle you can copy.

What the name means and where it comes from

Hoshin combines the Japanese characters for direction and needle, as in a compass needle, and is usually translated as direction or policy. Kanri means management or control. Put together, the phrase means something like managing by direction: setting a heading for the whole organisation and steering everyone towards it. The word policy in policy deployment carries that sense of direction and priorities, not rules or procedures.

The method grew up in Japanese manufacturing in the 1960s, as companies that had adopted total quality control looked for a way to connect company wide targets with daily improvement work. It drew on the plan, do, check, act cycle from quality management and on the management by objectives idea Peter Drucker set out in the 1950s. The difference was that it put more weight on how targets are reached, and on agreeing them through discussion rather than handing them down.

Western companies began adopting hoshin planning in the 1980s. An English edition of a book edited by Yoji Akao, published in 1991, helped bring the method to English speaking readers, and Thomas L. Jackson’s 2006 book for lean organisations sets out the X matrix in detail. Both are listed in the sources below.

How it works, step by step

Versions differ in the detail, but most follow the same sequence. The steps below assume a yearly cycle.

  1. Confirm the long term direction. Start from the organisation’s purpose and a clear view of where it needs to be in three to five years. If that is not agreed, stop here; the method deploys a strategy, it does not create one.
  2. Choose a few breakthrough objectives. These are the big changes that would make the most difference over three to five years, and they should require the organisation to work differently, not just harder. Keep to a handful at most.
  3. Set annual objectives. For each breakthrough objective, decide what must be achieved this year to stay on course, in terms specific enough to measure.
  4. Deploy through catchball. Each level of management proposes how it will contribute, which improvement projects it will run and how progress will be measured, then agrees this with the levels above and below.
  5. Do the work. Teams run the improvement projects alongside the day to day business, using plan, do, check, act to test and adjust as they go.
  6. Review monthly. Each level checks its measures, explains any misses and agrees countermeasures, using simple tools such as a fishbone diagram to find causes rather than blame.
  7. Reflect at year end. The leadership team looks honestly at what worked, what did not and why, and that reflection shapes the next year’s plan.

Most versions also separate two kinds of goal. Breakthrough objectives are the few things that must change. Business fundamentals, sometimes called daily management, are the measures that keep the operation healthy, such as safety, quality, cost and delivery. Hoshin effort goes on the first, while the second is run through normal performance management, and confusing the two is one of the quickest ways to overload the plan.

Catchball: agreeing targets in both directions

Catchball is the back and forth process by which plans are agreed between levels. Leaders propose an objective and pass it, like a ball, to the next level down. That team replies with what it believes it can achieve, what it would need and what it would change, and the ball goes back and forth until both sides agree a target and a plan they believe in.

It also runs sideways, between departments that depend on each other, so that a sales target is matched by the operational capacity to deliver it. Catchball takes time, especially in the first year, but it is where much of the value lies. People commit to targets they have helped to shape, and the conversations surface constraints a top down plan would miss.

The test of good catchball is whether anything changes. If every proposal comes back exactly as it went down, the organisation is collecting comments, not agreeing a plan.

The hoshin kanri X matrix explained

The X matrix puts a whole year’s plan on a single page. It is built around a large X that divides the centre into four areas, each holding one list, and small grids in the corners show how each item connects to the next. It is read clockwise, starting at the bottom:

  • Bottom: breakthrough objectives. The three to five year changes the organisation is committed to.
  • Left: annual objectives. What must be achieved this year to make progress on each breakthrough.
  • Top: improvement priorities. The projects and initiatives that will deliver the annual objectives.
  • Right: measures and targets. How progress on each priority will be tracked, with the target for the year.
  • Far right: resources. The teams or people who lead and support each priority.

The corner grids mark where items are linked, usually with symbols for a strong or weaker relationship. They make gaps obvious: an annual objective with no improvement priority behind it, a project that serves no objective, or a measure that tracks nothing on the plan. That is the matrix’s real value, because it forces the conversation about whether the plan actually adds up.

A simple hoshin kanri template you can copy

A full X matrix is hard to show on a web page, so the version below flattens it into rows. Each row traces one thread from a breakthrough objective to the person who owns the work. Copy it into a spreadsheet, add rows as needed and keep the total small.

Breakthrough objective (3 to 5 years)Annual objective (this year)Improvement priorityMeasure and targetLeadSupport
The big change you are committed toWhat must be true by year endThe project or initiative that gets you thereOne measure, its baseline and this year’s targetOne named personTeams that must contribute
Breakthrough 1Annual objective 1aPriority 1aMeasure, baseline, targetNameTeams
Breakthrough 1Annual objective 1bPriority 1bMeasure, baseline, targetNameTeams
Breakthrough 2Annual objective 2aPriority 2aMeasure, baseline, targetNameTeams

Two rules keep it honest. Every row needs a single named lead, and every measure needs a baseline before the year starts, because if you cannot measure where you are, you cannot show progress. Track the benefits alongside it with a benefits realisation plan template, so the matrix shows outcomes as well as activity.

The yearly planning cycle

This cycle assumes a financial year that starts in April. Shift the months to suit your own year.

WhenWhat happensWho is involved
December to JanuaryReflect on the current year: what was achieved, what was missed and why. Refresh the three to five year view.Executive team, with input from senior managers
January to FebruaryConfirm breakthrough objectives, draft annual objectives and start catchball with the next level down.Executive team and senior managers
February to MarchCatchball down and across: agree improvement priorities, measures, targets and owners, and align the budget.All management levels and finance
AprilPublish the matrix and team plans, and start the projects.Everyone
Every monthReview measures at each level, explain misses, agree countermeasures and escalate anything that needs a decision.Each management team
Every quarterReview the whole portfolio. Change targets or priorities only where the evidence demands it.Executive team

A worked example

This example is hypothetical. Imagine a field services business of around 1,200 people that maintains heating and electrical systems for housing associations and councils. Its leadership team agrees two breakthrough objectives for the next three years: make first time fixes the norm on every contract, and grow planned maintenance until it outweighs reactive repairs.

Breakthrough objectiveAnnual objectiveImprovement priorityMeasure and targetLeadSupport
First time fixes as the normRaise the first time fix rate from 72% to 82%Better triage at the contact centre so the right engineer is sentFirst time fix rate by contract, monthly; 82% by MarchHead of Customer ServiceOperations, IT
First time fixes as the normCorrect parts on the van for four in five jobsParts kits by job type, linked to schedulingJobs with correct parts on first visit; 80% by MarchSupply Chain ManagerOperations
Planned work outweighs reactiveMove two large contracts onto planned schedulesAsset condition surveys on both contractsShare of contract value from planned work; 35% by MarchCommercial DirectorEngineering, Finance

In the first round of catchball, operations managers in the two rural regions pushed back on the parts target, because travel distances made restocking vans much harder there. The leadership team kept the target but agreed to fund a second parts hub. The target stayed ambitious and the plan became believable, which is catchball doing its job.

By month four the first time fix rate was moving, but the parts measure was not. A short root cause analysis found that job codes in the scheduling system were too broad to drive the right kits. The countermeasure, a revised set of job codes, was given an owner in IT and a date, and the review moved on.

When to use it, and when not to

Hoshin kanri works best when an organisation has a clear strategy but struggles to turn it into consistent action across functions, when too many priorities compete for the same people, and when leaders can commit to a monthly review rhythm for at least a full year. It also needs a reasonably stable management structure to cascade through.

It is the wrong tool when the strategy itself is not agreed, because it deploys a direction rather than setting one; in that case, start with strategy consulting to make the choices first. It is also a poor fit for an organisation in crisis, where weekly decisions matter more than a yearly cycle, and for leadership teams that will not give time to catchball and reviews. Adding it on top of a planning process that already works usually creates paperwork rather than focus.

Common mistakes

  • Too many objectives. The point is focus. A matrix with fifteen breakthrough objectives is a list, not a strategy.
  • Catchball in name only. Targets are handed down with a request for comments, and nothing that comes back changes them.
  • Mixing breakthrough work with business as usual. Routine performance measures crowd out the few changes that matter.
  • Reviews that report activity, not results. Meetings list what was done instead of whether the measures moved and what will change if they did not. Our guide on how to read a programme status report covers the same trap.
  • Reviews that turn into blame. Once a miss leads to punishment, people stop reporting problems honestly and the reviews lose their value.
  • No link to the budget. Priorities without money or people behind them are wishes, and everyone knows it.
  • Treating the matrix as the goal. The X matrix is a record of the conversations. A tidy matrix with no reviews behind it changes nothing.

How hoshin fits with wider delivery work

Hoshin is one way to run strategy execution, not the only one. Its core principles apply whichever method you use: a few clear priorities, agreed ownership, measures tied to outcomes and a steady review rhythm. Our strategy execution work applies them with as much or as little formal structure as your organisation needs, and our operational excellence team connects the plan to daily improvement on the ground.

Where the projects in the matrix are big enough to need programme disciplines, such as governance, a PMO and independent assurance, our delivery excellence service covers them.

Common questions

What is hoshin kanri in simple terms?

Hoshin kanri is a way of making sure a whole organisation works on a few agreed priorities. Leaders set a small number of long term breakthrough objectives, turn them into annual goals, and agree with each level how it will contribute and how progress will be measured. Progress is reviewed every month, and the whole plan is revisited every year.

What is a hoshin kanri X matrix?

The X matrix is a one page planning tool used in hoshin kanri. It shows breakthrough objectives, annual objectives, improvement priorities and measures in four areas arranged around a central X, with grids in the corners showing how each item links to the next. A final section names who leads and supports each priority, so anyone can trace their work back to the strategy.

What is catchball in hoshin planning?

Catchball is the back and forth discussion used to agree objectives and targets between levels of an organisation. A proposal is passed down, the receiving team replies with what it can achieve and what it needs, and the discussion continues until both sides agree. It also runs across departments that depend on each other. The aim is targets that are ambitious, realistic and genuinely owned.

What is the difference between hoshin kanri and OKRs?

Both connect goals across an organisation, but they work differently. Hoshin kanri runs on a yearly cycle tied to three to five year breakthrough objectives, agrees targets through catchball and reviews them monthly. OKRs usually run quarterly, are often set partly by teams themselves and are commonly written as stretch goals. Hoshin is more structured and suits organisations that want tight alignment.

Is there a simple hoshin kanri template?

Yes. The classic template is the X matrix, which fits a year’s plan on one page. A simpler option is a table where each row traces one thread from a breakthrough objective to an annual objective, an improvement priority, a measure and a named lead. This page includes a copyable version of that table, plus a yearly planning cycle you can adapt.

Related reading: Gap analysis explained, The McKinsey 7S model, Value chain analysis and What a good programme sponsor does.

Need your strategy to show up in the work?

We help leadership teams turn a few clear priorities into agreed targets, funded projects and a review rhythm that lasts beyond the first quarter. Talk to us about your planning cycle.

Book a confidential conversation

Sources: Yoji Akao (ed.), Hoshin Kanri: Policy Deployment for Successful TQM, Productivity Press, 1991; Thomas L. Jackson, Hoshin Kanri for the Lean Enterprise: Developing Competitive Capabilities and Managing Profit, Productivity Press, 2006; Peter F. Drucker, The Practice of Management, 1954

PEF TRACK RECORD£13bnLargestprogramme led5Continentsdelivered across19 yrsSystems delivery£25mLargestsingle saving
CF

Written by Christopher Fagan

Managing Partner, PEF Consulting Partners

Christopher has led systems and transformation delivery for 19 years, including the National Grid separation, the £9bn Energy Bills Support Scheme and the BP Pulse EV charging rollout.